07-05-2024 Electrical release in Terminal T2

The Ministry of Electricity, Water and Renewable Energy announces that the Ministry, today, in coordination with the Ministry of Public Works, launched the electrical current for the new airport project (T2) by connecting the feeders to the two main power stations that feed the new airport project with (24) 11 KV feeders, after completing all Procedures related to the examination before the process of delivering electrical current.

Note that the connection stations will feed the substations feeding the new airport facilities, which were implemented by the Ministry of Public Works.